Hi Experts,
I have created one Single cycle plan as shown in the below pic.
My issue is- Every time when I execute IP30 (Deadline monitoring) transaction, for the maintenance plan 51. Call object (Mntc Order) is getting created.
If I repeat the execution of IP30 in the same day Mntc Order is keep creating new. Hence multiple Mntc orders are available from the same Mntc plan for the same date.
Is this functionality is standard or not?
I want to restrict 1 Mntc order for the Mntc plan per day even if i run IP30 repeatedly for the same day. is there any configuration available?
Thank you
Renjith NK