Re: What is the impact of the availability confirmation in MDVP for Process Order and how to reverse if any?

Hi B Brahmankar,

 

From the screenshot below, the commitment has been past due.

 

You are right that the planned order still is valid with firm indicator.

Image may be NSFW.
Clik here to view.
Capture.PNG

 

If left as it is now, what is the impact on the planning? The quantity in the firmed order is regarded as Demand even though it is not converted to Production order or PR?

 

Pls kindly confirm.

 

Sally.

 

P.S. The planned order is on other plant. If there is no much impact, I would not bother to ask for help with the firm indicator on the planned order.