Hi Subba,
Yes.
1) Change annual estimate
2) check the last performed work order was at what reading. Enter that reading as a cumulative value. Replace counter with current reading.
Example :
Say meter reading on
17th May = 30000 HR,
18th May = 30021 HR.
Suppose you need to start your plan on 17th May ( When existing counter reading was 30021 HR)
So in this case, You need to
- Replace counter ( IK11 - edit - replace counter - Tottal counter reading set externally) with reading value as 30021 HR ( from 18th May) & Total counter reading as 30000 HR ( from 17th May)
- IP02 - Add scheduling period say 365 days.
- Now go to IP10, restart the plan with start counter reading as 30000.
Co-relate this case with your situation and try to perform steps accordingly.
Hope this helps.
Regards,
Amol