Hi Subba,

 

Yes.

 

1) Change annual estimate

2) check the last performed work order was at what reading. Enter that reading as a cumulative value. Replace counter with current reading.

 

Example :

 

Say meter reading on

 

17th May  = 30000 HR,

18th May = 30021 HR.

 

Suppose you need to start your plan on 17th May ( When existing counter reading was 30021 HR)

 

So in this case, You need to

 

  • Replace counter ( IK11 - edit - replace counter - Tottal counter reading set externally)  with reading value as 30021 HR ( from 18th May) & Total counter reading as 30000 HR ( from 17th May)
  • IP02 - Add scheduling period say 365 days.
  • Now go to IP10, restart the plan with start counter reading as 30000.

 

Co-relate this case with your situation and try to perform steps accordingly.

 

 

Hope this helps.

 

 