Re: MRP Type V1 is not considering External Req.

$
0
0

Hi,

 

Following the link in below statement i have some questions,

 

Features

Sales orders and manual reservations are included in planning during the replenishment lead time . In Customizing you can also enter settings for the respective MRP type, so that

 

Point 1

  • sales orders and manual reservations are included in planning not just during the replenishment lead time but during the whole horizon.


Screen 1

Clip 1.PNG

Point 2

  • alongside sales orders and manual reservations various other requirements are taken into account in the material requirements planning.


Screen 2

Clip 2.PNG

 

Screen 1 Setting equates Point 1.

 

Screen 2 Setting equates Point 2.

 

To my requirement in previous post you want me activate Order Reservation, Fine Its Working. But

 

Questions:

 

1.     What can expect for Screen 1 setting in MRP Type V1 for ROH, Bcz Sales Order is Not possible for ROH is the condition exclude about Manual Reservation, HALB & FERT.

 

          In such case, Screen 1 setting alone will not make any functional difference from VB, IS IT SO...?

 

Thanks With Regards,

Dinesh Kumar V.

 

 

 

 