Hi,
Following the link in below statement i have some questions,
Features
Sales orders and manual reservations are included in planning during the replenishment lead time . In Customizing you can also enter settings for the respective MRP type, so that
Point 1
- sales orders and manual reservations are included in planning not just during the replenishment lead time but during the whole horizon.
Screen 1
Point 2
- alongside sales orders and manual reservations various other requirements are taken into account in the material requirements planning.
Screen 2
Screen 1 Setting equates Point 1.
Screen 2 Setting equates Point 2.
To my requirement in previous post you want me activate Order Reservation, Fine Its Working. But
Questions:
1. What can expect for Screen 1 setting in MRP Type V1 for ROH, Bcz Sales Order is Not possible for ROH is the condition exclude about Manual Reservation, HALB & FERT.
In such case, Screen 1 setting alone will not make any functional difference from VB, IS IT SO...?
Thanks With Regards,